Post by bennyp81 on Jun 15, 2005 11:11:29 GMT -8
Bart Reed
User ID: 1606604 Apr 19th 4:57 PM
San Mateo Daily Journal: Friday, April 18, 2003
BART-SFO opening set for June 22
By Dana Yates
Staff Writer
The wait is finally over for the grand opening of the BART-SFO extension scheduled to open to the public June 22, said BART spokesman Mike Healey.
After two years of delays and several missed targets for a grand opening, the $1.5 billion extension -- including the San Bruno, Millbrae and SFO stations -- is just two months away from public use, if all goes as planned.
After numerous delays written off as minor mishaps, BART officials are betting all testing runs smoothly during the next two months.
The project was officially handed over to BART this week by the contractor, Tutor-Saliba, who ran
up over $8 million dollars in late fines--$65,000
a day since November 2001. Those fees will likely be negotiated to a lower amount, said Healey.
BART must conduct eight to 12 weeks worth of tests before stations can open to the public. Starting today, BART has nine weeks and two
days to complete all testing. Some tests have already begun, said Healey.
"So far it's gone very well with the testing. We would not have set a date unless we were really confident," said Healey.
BART officials have been confident in the past, setting opening dates for Dec. 2001, then spring of 2002 and fall 2002. The project was pushed off so many times officials stopped setting new grand-opening dates. Their newfound confidence isn't enough for some people.
"The only way they could make that date is if God smiled proudly on this project and everything went right," said San Bruno resident Alice Barnes, who has been following the project for nine years. "That many years tells me it ain't going to happen."
Barnes, a retired government contract negotiator, has been waiting for BART to move down the Peninsula for years. Having just undergone
a quadruple bypass surgery, she wonders if she'll be around to see ride BART.
"I'm not sure if I'm going to make it for the grand opening, of all the people in this area I sure as hell deserve a ride on BART. But it's not going to happen until after Labor Day," said Barnes.
But BART officials are holding their position, already planning the grand opening celebrations for June 22 and an official ribbon cutting with city, state, and federal officials on hand June 21. A public open house will be held on May 6.
E-mail Dana Yates:dana@smdailyjournal.com or by phone: (650) 344-5200 ext. 106. What do you think of this story? Send a letter to the editor: Letters@smdailyjournal.com
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 5:08 PM
And some wonder why MTA isn't telling you the date for the opening of the Gold Line. 'Nuff said.
San Francisco Chronicle: Friday, April 18, 2003
BART to link to SFO June 22
After many delays, latest date is firm, transit officials say
By Michael Cabanatuan
Chronicle Staff Writer
The mystery that has vexed Bay Area residents and visitors alike for months, even years, has finally been answered.
June 22 is the day that BART's extension to San Francisco International Airport will open to the public.
After decades of planning, months of delays and a couple of squashed endangered garter snakes, BART officials -- joined by a passel of politicians -- announced the opening date Thursday by pulling a sheet off a sign reading: "BART to SFO ... BART to the world, June 22, 2003."
"It has taken about 47 years to get to this point," said Pete Snyder, president of the BART Board of Directors, referring to a 1956 study that
recommended construction of BART with a link to the airport. "But when that first train glides into the airport, it will have been worth the wait."
This is not the first time BART officials have given a projected opening date for the 8.7-mile, four-station SFO extension, though it is the most specific. When BART broke ground in November 1997,
officials predicted that the first train would roll down the Peninsula from Colma and into SFO's international terminal by the end of 2001.
But weather -- and the endangered snakes that were
crushed at a construction site -- forced BART to push the starting date back to late fall 2002.
Then in July of last year, BART officials admitted they wouldn't be able to open in time for the holidays and predicted a January start.
In early January, they backed off that promise and refused to do any more speculating until contractor Tutor-Saliba/Slattery completed the
project and handed it over to BART for final testing.
That finally happened Monday -- and BART officials set the opening date.
"It's not going to change again, is it?" joked San Francisco Mayor Willie Brown, as he arrived at an Embarcadero station ceremony to
announce the opening date. "You guys keep changing the date."
BART officials assured the mayor he would be able to ride a train into SFO on June 22 -- the second day of summer.
"We're sure the opening date is going to stick," said Tom Margro, BART's general manager.
8 WEEKS OF TESTING
While the contractors have tested the components of the extension, BART will now begin about eight weeks of comprehensive testing, running trains from other parts of the system onto the extension as if it were in service.
"We'll be running trains, we'll have people out there in (station agent) booths, we'll be making sure everybody knows where everything is," Margro said.
The official opening day -- a Sunday -- will be preceded by a couple of celebratory openings: a private reception on June 20 and a public
ceremony on June 21.
"This will be not only a benefit to tourists and visitors to our city but to residents of the Bay Area who will be able to hop on a train and get to the airport," said James Fang, a BART director who said he'd pushed for the SFO extension since joining the board in 1990.
4 NEW STATIONS
While everyone refers to the extension as the SFO extension, the airport is just one of four stations. Heading south from Colma, trains will stop in South San Francisco and San Bruno, with some heading straight to the airport and others heading to Millbrae, a major transit hub where BART will share a station with Caltrain.
A shuttle train will carry passengers between Millbrae and the airport.
[The paid BART shuttle will replace a free-to-ride shuttle <www.transitinfo.org/Sched/CX/SFO/D> operated by SFO between Millbrae Caltrain and multiple SFO destinations.]
Trains on the Dublin/Pleasanton line will serve SFO directly, with Pittsburg/Bay Point line trains heading to Millbrae. But Margro said
some Pittsburg/Bay Point trains might be scheduled for direct trips to and from SFO.
Passengers on other lines would need to either transfer to a direct train to get to the airport or catch the shuttle train in Millbrae.
"The opening of the extension means you can go from home to Rome, or any other destination in the
world," said San Mateo County Supervisor Mike Nevin, who worked to bring BART into his county.
"And BART is our connection to the world."
E-mail Michael Cabanatuan at
mcabanatuan@sfchronicle.com
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 9:41 PM
San Mateo County Times: Friday, April 18, 2003
BART extension to open June 22; After years of conflict, construction, $1.5 billion airport extension will finally begin operations
By Justin Jouvenal
Staff Writer
SAN FRANCISCO -- The $1.5 billion San Francisco Airport extension is now scheduled to open June 22 after roughly five years of construction, budget battles and political squabbles.
The much-anticipated -- and often delayed project -- will give the Bay Area one of the nation's first direct-rail connections to a major
international airport.
Conceived nearly 50 years ago, it was one of the largest ongoing construction projects in the Bay Area.
"We've had to overcome obstacles of almost biblical proportions, whether human greed of airline executives, snakes and endangered
species, or mudslides," said Dan Richard, a BART director from Contra Costa County.
Richard was joined Thursday by San Francisco Mayor Willie Brown, San Mateo County Supervisor Mike Nevin and a host of other local officials to announce the extension opening at the Embarcadero BART Station.
The 8.7-mile line will add four new stations: South San Francisco, San Bruno, SFO and Millbrae.
Trains will whisk passengers directly into SFO's International Terminal just a few minutes' walk from many ticket counters and gates.
Passengers will also be able to connect to AirTrain, SFO's new people-mover, to get to the rest of the airport.
In Millbrae, BART will link with Caltrain across a platform, giving riders the ability to travel from Pittsburg to Gilroy -- and dozens of points in between -- on the rails.
"Transportation is all about a seamless connection," Supervisor Mike Nevin said. "(The extension) means you can go from home to Rome. This is our pathway to the world."
BART officials plan to hold a public dedication ceremony to mark the extension on Saturday, June 21. On May 3, BART will unveil the public art
featured in the Millbrae station.
BART broke ground on the project in 1997, but the bulk of the work did not begin until a year later when joint venture Tutor-Saliba/Slattery won the lead contract, which was worth $620 million.
Crews excavated 1.9 million feet of soil to make way for the subway tunnel -- enough to fill a 50-story building covering a whole city block. And 50,000 tons of reinforcing steel was used to construct the subway box.
But the project also ran into snags. The BART-SFO extension was originally slated to open in December 2001, but that date was pushed back because construction was slowed by heavy rains and the deaths of two endangered San Francisco garter snakes on work sites.
The death of the first snake in April 2000 shut down construction for 18 days, costing BART about $1 million. Other delays pushed the opening to the end of 2002 and then into this year.
Tutor-Saliba/Slattery gave BART the all-clear sign on Monday.
County residents will see empty BART trains running up and down the extension between now and the opening. The trips are dress rehearsals
that are part of the final round of BART testing.
Despite earlier glitches, BART officials said there's no chance the opening will be delayed beyond the end of June.
"This (date) is a brick wall," said Molly MacArthur, a BART spokeswoman.
The $1.5 billion extension was paid for with a variety of funds. The federal government picked up about $750 million, while the state,
SFO, regional agencies and the County footed the rest of the bill.
It will cost $4.70 to ride from downtown San Francisco to SFO. A ride from downtown Oakland will cost $4.95. By 2010, BART officials expect
about 70,000 riders a day to use the extension.
Speaking to Bay area officials, San Francisco Mayor Willie Brown hinted Thursday there could be another push for a BART extension beyond Millbrae.
"It would not surprise me in the not too distant future if you were issued the challenge to complete the public transit encirclement of
the whole Bay area," Brown said.
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 11:25 PM
San Francisco Examiner: Friday, April 18, 2003
Editorial: BART-to-SFO finally a reality
After years of debate, planning and construction, BART will finally send its first trains to the new station at the San Francisco International Airport on June 22, 2003.
It will be a momentous event. San Francisco will become one of the few cities in the world to have an underground transit system go directly into a major airport, and the BART-to-SFO link, along with the opening of other San Mateo County BART stations, is expected to provide an economic boost to the region.
For local residents, it will provide a wonder-fully efficient and affordable way to get to the airport.
Travelers will be able to hop on a train at their nearby neighborhood BART station and disembark in an airport terminal a half-hour later, just a short walk from the ticket counter.
For many Bay Area residents, the travel experience will begin and end in an entirely new and terrific way.
It's been a long and grueling road, fraught with political and funding potholes, but now it's just about done. It goes to show that major projects can still happen here.
Þ-®-Þ-®-Þ
User ID: 1606604 Apr 19th 4:57 PM
San Mateo Daily Journal: Friday, April 18, 2003
BART-SFO opening set for June 22
By Dana Yates
Staff Writer
The wait is finally over for the grand opening of the BART-SFO extension scheduled to open to the public June 22, said BART spokesman Mike Healey.
After two years of delays and several missed targets for a grand opening, the $1.5 billion extension -- including the San Bruno, Millbrae and SFO stations -- is just two months away from public use, if all goes as planned.
After numerous delays written off as minor mishaps, BART officials are betting all testing runs smoothly during the next two months.
The project was officially handed over to BART this week by the contractor, Tutor-Saliba, who ran
up over $8 million dollars in late fines--$65,000
a day since November 2001. Those fees will likely be negotiated to a lower amount, said Healey.
BART must conduct eight to 12 weeks worth of tests before stations can open to the public. Starting today, BART has nine weeks and two
days to complete all testing. Some tests have already begun, said Healey.
"So far it's gone very well with the testing. We would not have set a date unless we were really confident," said Healey.
BART officials have been confident in the past, setting opening dates for Dec. 2001, then spring of 2002 and fall 2002. The project was pushed off so many times officials stopped setting new grand-opening dates. Their newfound confidence isn't enough for some people.
"The only way they could make that date is if God smiled proudly on this project and everything went right," said San Bruno resident Alice Barnes, who has been following the project for nine years. "That many years tells me it ain't going to happen."
Barnes, a retired government contract negotiator, has been waiting for BART to move down the Peninsula for years. Having just undergone
a quadruple bypass surgery, she wonders if she'll be around to see ride BART.
"I'm not sure if I'm going to make it for the grand opening, of all the people in this area I sure as hell deserve a ride on BART. But it's not going to happen until after Labor Day," said Barnes.
But BART officials are holding their position, already planning the grand opening celebrations for June 22 and an official ribbon cutting with city, state, and federal officials on hand June 21. A public open house will be held on May 6.
E-mail Dana Yates:dana@smdailyjournal.com or by phone: (650) 344-5200 ext. 106. What do you think of this story? Send a letter to the editor: Letters@smdailyjournal.com
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 5:08 PM
And some wonder why MTA isn't telling you the date for the opening of the Gold Line. 'Nuff said.
San Francisco Chronicle: Friday, April 18, 2003
BART to link to SFO June 22
After many delays, latest date is firm, transit officials say
By Michael Cabanatuan
Chronicle Staff Writer
The mystery that has vexed Bay Area residents and visitors alike for months, even years, has finally been answered.
June 22 is the day that BART's extension to San Francisco International Airport will open to the public.
After decades of planning, months of delays and a couple of squashed endangered garter snakes, BART officials -- joined by a passel of politicians -- announced the opening date Thursday by pulling a sheet off a sign reading: "BART to SFO ... BART to the world, June 22, 2003."
"It has taken about 47 years to get to this point," said Pete Snyder, president of the BART Board of Directors, referring to a 1956 study that
recommended construction of BART with a link to the airport. "But when that first train glides into the airport, it will have been worth the wait."
This is not the first time BART officials have given a projected opening date for the 8.7-mile, four-station SFO extension, though it is the most specific. When BART broke ground in November 1997,
officials predicted that the first train would roll down the Peninsula from Colma and into SFO's international terminal by the end of 2001.
But weather -- and the endangered snakes that were
crushed at a construction site -- forced BART to push the starting date back to late fall 2002.
Then in July of last year, BART officials admitted they wouldn't be able to open in time for the holidays and predicted a January start.
In early January, they backed off that promise and refused to do any more speculating until contractor Tutor-Saliba/Slattery completed the
project and handed it over to BART for final testing.
That finally happened Monday -- and BART officials set the opening date.
"It's not going to change again, is it?" joked San Francisco Mayor Willie Brown, as he arrived at an Embarcadero station ceremony to
announce the opening date. "You guys keep changing the date."
BART officials assured the mayor he would be able to ride a train into SFO on June 22 -- the second day of summer.
"We're sure the opening date is going to stick," said Tom Margro, BART's general manager.
8 WEEKS OF TESTING
While the contractors have tested the components of the extension, BART will now begin about eight weeks of comprehensive testing, running trains from other parts of the system onto the extension as if it were in service.
"We'll be running trains, we'll have people out there in (station agent) booths, we'll be making sure everybody knows where everything is," Margro said.
The official opening day -- a Sunday -- will be preceded by a couple of celebratory openings: a private reception on June 20 and a public
ceremony on June 21.
"This will be not only a benefit to tourists and visitors to our city but to residents of the Bay Area who will be able to hop on a train and get to the airport," said James Fang, a BART director who said he'd pushed for the SFO extension since joining the board in 1990.
4 NEW STATIONS
While everyone refers to the extension as the SFO extension, the airport is just one of four stations. Heading south from Colma, trains will stop in South San Francisco and San Bruno, with some heading straight to the airport and others heading to Millbrae, a major transit hub where BART will share a station with Caltrain.
A shuttle train will carry passengers between Millbrae and the airport.
[The paid BART shuttle will replace a free-to-ride shuttle <www.transitinfo.org/Sched/CX/SFO/D> operated by SFO between Millbrae Caltrain and multiple SFO destinations.]
Trains on the Dublin/Pleasanton line will serve SFO directly, with Pittsburg/Bay Point line trains heading to Millbrae. But Margro said
some Pittsburg/Bay Point trains might be scheduled for direct trips to and from SFO.
Passengers on other lines would need to either transfer to a direct train to get to the airport or catch the shuttle train in Millbrae.
"The opening of the extension means you can go from home to Rome, or any other destination in the
world," said San Mateo County Supervisor Mike Nevin, who worked to bring BART into his county.
"And BART is our connection to the world."
E-mail Michael Cabanatuan at
mcabanatuan@sfchronicle.com
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 9:41 PM
San Mateo County Times: Friday, April 18, 2003
BART extension to open June 22; After years of conflict, construction, $1.5 billion airport extension will finally begin operations
By Justin Jouvenal
Staff Writer
SAN FRANCISCO -- The $1.5 billion San Francisco Airport extension is now scheduled to open June 22 after roughly five years of construction, budget battles and political squabbles.
The much-anticipated -- and often delayed project -- will give the Bay Area one of the nation's first direct-rail connections to a major
international airport.
Conceived nearly 50 years ago, it was one of the largest ongoing construction projects in the Bay Area.
"We've had to overcome obstacles of almost biblical proportions, whether human greed of airline executives, snakes and endangered
species, or mudslides," said Dan Richard, a BART director from Contra Costa County.
Richard was joined Thursday by San Francisco Mayor Willie Brown, San Mateo County Supervisor Mike Nevin and a host of other local officials to announce the extension opening at the Embarcadero BART Station.
The 8.7-mile line will add four new stations: South San Francisco, San Bruno, SFO and Millbrae.
Trains will whisk passengers directly into SFO's International Terminal just a few minutes' walk from many ticket counters and gates.
Passengers will also be able to connect to AirTrain, SFO's new people-mover, to get to the rest of the airport.
In Millbrae, BART will link with Caltrain across a platform, giving riders the ability to travel from Pittsburg to Gilroy -- and dozens of points in between -- on the rails.
"Transportation is all about a seamless connection," Supervisor Mike Nevin said. "(The extension) means you can go from home to Rome. This is our pathway to the world."
BART officials plan to hold a public dedication ceremony to mark the extension on Saturday, June 21. On May 3, BART will unveil the public art
featured in the Millbrae station.
BART broke ground on the project in 1997, but the bulk of the work did not begin until a year later when joint venture Tutor-Saliba/Slattery won the lead contract, which was worth $620 million.
Crews excavated 1.9 million feet of soil to make way for the subway tunnel -- enough to fill a 50-story building covering a whole city block. And 50,000 tons of reinforcing steel was used to construct the subway box.
But the project also ran into snags. The BART-SFO extension was originally slated to open in December 2001, but that date was pushed back because construction was slowed by heavy rains and the deaths of two endangered San Francisco garter snakes on work sites.
The death of the first snake in April 2000 shut down construction for 18 days, costing BART about $1 million. Other delays pushed the opening to the end of 2002 and then into this year.
Tutor-Saliba/Slattery gave BART the all-clear sign on Monday.
County residents will see empty BART trains running up and down the extension between now and the opening. The trips are dress rehearsals
that are part of the final round of BART testing.
Despite earlier glitches, BART officials said there's no chance the opening will be delayed beyond the end of June.
"This (date) is a brick wall," said Molly MacArthur, a BART spokeswoman.
The $1.5 billion extension was paid for with a variety of funds. The federal government picked up about $750 million, while the state,
SFO, regional agencies and the County footed the rest of the bill.
It will cost $4.70 to ride from downtown San Francisco to SFO. A ride from downtown Oakland will cost $4.95. By 2010, BART officials expect
about 70,000 riders a day to use the extension.
Speaking to Bay area officials, San Francisco Mayor Willie Brown hinted Thursday there could be another push for a BART extension beyond Millbrae.
"It would not surprise me in the not too distant future if you were issued the challenge to complete the public transit encirclement of
the whole Bay area," Brown said.
Þ--Þ--Þ
Bart Reed
User ID: 1606604 Apr 19th 11:25 PM
San Francisco Examiner: Friday, April 18, 2003
Editorial: BART-to-SFO finally a reality
After years of debate, planning and construction, BART will finally send its first trains to the new station at the San Francisco International Airport on June 22, 2003.
It will be a momentous event. San Francisco will become one of the few cities in the world to have an underground transit system go directly into a major airport, and the BART-to-SFO link, along with the opening of other San Mateo County BART stations, is expected to provide an economic boost to the region.
For local residents, it will provide a wonder-fully efficient and affordable way to get to the airport.
Travelers will be able to hop on a train at their nearby neighborhood BART station and disembark in an airport terminal a half-hour later, just a short walk from the ticket counter.
For many Bay Area residents, the travel experience will begin and end in an entirely new and terrific way.
It's been a long and grueling road, fraught with political and funding potholes, but now it's just about done. It goes to show that major projects can still happen here.
Þ-®-Þ-®-Þ