Post by metrocenter on Jul 5, 2018 14:01:01 GMT -8
Unfortunate for all of Los Angeles, but tutor perini also won the contract for phase three, the purple line is so screwed. An unforeseen delay has already occurred for the infamous tutor perini at century city, so an eighteen month road closure of constellation isn’t beginning until August. Since metro so dumbly awarded the contract to them, I expect phase two and phase three to be completed six years late and six billion over budget—each. But TP is proceeding with demolition for he staging area while school is out for the summer at BHHS, since it is TP I’m surprised they did t screw that up too and get themselves a year delay as a result! I do not feel good at all about the hiring of Tutor-Perini, or Tutor-Saliba, or whatever they call themselves these days. That company just got called out in San Francisco for using the wrong kind of rails on the Central Subway project. The rails are now being pulled out and replaced. It's a big cause for concern when a proposal like Tutor's Phase III proposal comes in so cheap. Hopefully Metro's lawyers made the contract with Tutor air-tight.
|
|
|
Post by culvercitylocke on Jul 5, 2018 14:12:06 GMT -8
Unfortunate for all of Los Angeles, but tutor perini also won the contract for phase three, the purple line is so screwed. An unforeseen delay has already occurred for the infamous tutor perini at century city, so an eighteen month road closure of constellation isn’t beginning until August. Since metro so dumbly awarded the contract to them, I expect phase two and phase three to be completed six years late and six billion over budget—each. But TP is proceeding with demolition for he staging area while school is out for the summer at BHHS, since it is TP I’m surprised they did t screw that up too and get themselves a year delay as a result! I do not feel good at all about the hiring of Tutor-Perini, or Tutor-Saliba, or whatever they call themselves these days. That company just got called out in San Francisco for using the wrong kind of rails on the Central Subway project. The rails are now being pulled out and replaced. It's a big cause for concern when a proposal like Tutor's Phase III proposal comes in so cheap. Hopefully Metro's lawyers made the contract with Tutor air-tight. I imagine a private firm has much better and many more lawyers than a public utility. I think tutor is also working on the HSR. And they built some MSE bridge abutments that were of such low quality that they are being removed and replaced with cast in place concrete abutments. Wasn’t tutor also responsible for the worst tunneling construction f**k up in the USA the Alaskan way viaduct? And let’s not forget how badly they built he metro red line!
|
|
|
Post by numble on Jul 15, 2018 19:43:40 GMT -8
Here is the status of the Purple Line Extension Segment 1 (as of July 2018): • Overall Project Progress is 37% complete. • At the Wilshire/Western Retrieval Shaft, excavation and bracing continues with Level A strut installation and utility hanging in the south, and Level B waler installation in the north. • Concrete wall pours at Wilshire/La Brea Station needed to support TBM assembly are scheduled to complete at end of June 2018. Installation of rebar, embeds and HDPE continue along with mining support equipment in the south yard. • Excavation to Level D at the Wilshire/Fairfax Station continues, along with waler and strut installation. Excavation is now clear of the Paleo zone (Elevation 105’). Alimak installation to Level C and work on the pipe canopy tunnel eye is in progress. • Station excavation under the concrete deck at Wilshire/La Cienega Station continues. Work on the permanent power duct bank and hanging utilities moves forward. • Tunnel Boring Machines (TBMs) were delivered to Los Angeles in December 2017. TBM assembly at Wilshire/La Brea Station is scheduled for July 2018. Tunneling is planned to start in September 2018. Projected cost: $3,154M Projected opening: Nov 2023 metro.legistar.com/View.ashx?M=F&ID=6364702&GUID=15E9B6E8-1824-432E-8E0B-578E5BBA349BThis project seems to be moving at a much faster pace compared to the Crenshaw, Regional Connector, and Purple Line Section 2. In January, this was the completion percentage of the 4 projects: Crenshaw: 75% Regional Connector: 43% Purple Line Section 1: 25% Purple Line Section 2: 5% (Design 44% complete) metro.legistar.com/View.ashx?M=F&ID=5733197&GUID=CABC793F-86ED-47CB-901E-2DB239AC4813In July, this is the completion percentage of the 3 projects: Crenshaw: 81.8% Regional Connector: 51% Purple Line Section 1: 37% Purple Line Section 2: 7% (Design 66% complete)
|
|
|
Post by culvercitylocke on Jul 16, 2018 8:24:03 GMT -8
Here is the status of the Purple Line Extension Segment 1 (as of July 2018): • Overall Project Progress is 37% complete. • At the Wilshire/Western Retrieval Shaft, excavation and bracing continues with Level A strut installation and utility hanging in the south, and Level B waler installation in the north. • Concrete wall pours at Wilshire/La Brea Station needed to support TBM assembly are scheduled to complete at end of June 2018. Installation of rebar, embeds and HDPE continue along with mining support equipment in the south yard. • Excavation to Level D at the Wilshire/Fairfax Station continues, along with waler and strut installation. Excavation is now clear of the Paleo zone (Elevation 105’). Alimak installation to Level C and work on the pipe canopy tunnel eye is in progress. • Station excavation under the concrete deck at Wilshire/La Cienega Station continues. Work on the permanent power duct bank and hanging utilities moves forward. • Tunnel Boring Machines (TBMs) were delivered to Los Angeles in December 2017. TBM assembly at Wilshire/La Brea Station is scheduled for July 2018. Tunneling is planned to start in September 2018. Projected cost: $3,154M Projected opening: Nov 2023 metro.legistar.com/View.ashx?M=F&ID=6364702&GUID=15E9B6E8-1824-432E-8E0B-578E5BBA349BThis project seems to be moving at a much faster pace compared to the Crenshaw, Regional Connector, and Purple Line Section 2. In January, this was the completion percentage of the 4 projects: Crenshaw: 75% Regional Connector: 43% Purple Line Section 1: 25% Purple Line Section 2: 5% (Design 44% complete) metro.legistar.com/View.ashx?M=F&ID=5733197&GUID=CABC793F-86ED-47CB-901E-2DB239AC4813In July, this is the completion percentage of the 3 projects: Crenshaw: 81.8% Regional Connector: 51% Purple Line Section 1: 37% Purple Line Section 2: 7% (Design 66% complete) It’s moving faster because it is skansa, not one of the criminal groups running the other projects. Skansa left a surplus of $200,000,000 from building expo, money that is being given to the tutor criminals for purple phase two, presumably because they’ve already defrauded that much money from tax payers.
|
|
|
Post by metrocenter on Jul 16, 2018 10:17:26 GMT -8
Here is the status of the Purple Line Extension Segment 1 (as of July 2018): • Overall Project Progress is 37% complete. • At the Wilshire/Western Retrieval Shaft, excavation and bracing continues with Level A strut installation and utility hanging in the south, and Level B waler installation in the north. • Concrete wall pours at Wilshire/La Brea Station needed to support TBM assembly are scheduled to complete at end of June 2018. Installation of rebar, embeds and HDPE continue along with mining support equipment in the south yard. • Excavation to Level D at the Wilshire/Fairfax Station continues, along with waler and strut installation. Excavation is now clear of the Paleo zone (Elevation 105’). Alimak installation to Level C and work on the pipe canopy tunnel eye is in progress. • Station excavation under the concrete deck at Wilshire/La Cienega Station continues. Work on the permanent power duct bank and hanging utilities moves forward. • Tunnel Boring Machines (TBMs) were delivered to Los Angeles in December 2017. TBM assembly at Wilshire/La Brea Station is scheduled for July 2018. Tunneling is planned to start in September 2018. Projected cost: $3,154M Projected opening: Nov 2023 metro.legistar.com/View.ashx?M=F&ID=6364702&GUID=15E9B6E8-1824-432E-8E0B-578E5BBA349BThis project seems to be moving at a much faster pace compared to the Crenshaw, Regional Connector, and Purple Line Section 2. In January, this was the completion percentage of the 4 projects: Crenshaw: 75% Regional Connector: 43% Purple Line Section 1: 25% Purple Line Section 2: 5% (Design 44% complete) metro.legistar.com/View.ashx?M=F&ID=5733197&GUID=CABC793F-86ED-47CB-901E-2DB239AC4813In July, this is the completion percentage of the 3 projects: Crenshaw: 81.8% Regional Connector: 51% Purple Line Section 1: 37% Purple Line Section 2: 7% (Design 66% complete) The Regional Connector continues to plod along at a rate of 16% completion per year. Meanwhile, Purple Line Section 1 is moving forward at 24% completion per year. If these rates were to hold, both projects would complete at nearly the same time (late 2021 vs early 2022). Obviously there are very different issues between the projects. In some ways the Regional Connector is a much more difficult project, due to the ancient utilities in Downtown L.A., the variety of station types, and the coming construction of new portals and bridge in Little Tokyo. The Purple Line, OTOH, is a straight shot, all underground, with major utilities only crossing its path at major arteries.
|
|
|
Post by numble on Jul 16, 2018 10:58:42 GMT -8
Here is the status of the Purple Line Extension Segment 1 (as of July 2018): • Overall Project Progress is 37% complete. • At the Wilshire/Western Retrieval Shaft, excavation and bracing continues with Level A strut installation and utility hanging in the south, and Level B waler installation in the north. • Concrete wall pours at Wilshire/La Brea Station needed to support TBM assembly are scheduled to complete at end of June 2018. Installation of rebar, embeds and HDPE continue along with mining support equipment in the south yard. • Excavation to Level D at the Wilshire/Fairfax Station continues, along with waler and strut installation. Excavation is now clear of the Paleo zone (Elevation 105’). Alimak installation to Level C and work on the pipe canopy tunnel eye is in progress. • Station excavation under the concrete deck at Wilshire/La Cienega Station continues. Work on the permanent power duct bank and hanging utilities moves forward. • Tunnel Boring Machines (TBMs) were delivered to Los Angeles in December 2017. TBM assembly at Wilshire/La Brea Station is scheduled for July 2018. Tunneling is planned to start in September 2018. Projected cost: $3,154M Projected opening: Nov 2023 metro.legistar.com/View.ashx?M=F&ID=6364702&GUID=15E9B6E8-1824-432E-8E0B-578E5BBA349BThis project seems to be moving at a much faster pace compared to the Crenshaw, Regional Connector, and Purple Line Section 2. In January, this was the completion percentage of the 4 projects: Crenshaw: 75% Regional Connector: 43% Purple Line Section 1: 25% Purple Line Section 2: 5% (Design 44% complete) metro.legistar.com/View.ashx?M=F&ID=5733197&GUID=CABC793F-86ED-47CB-901E-2DB239AC4813In July, this is the completion percentage of the 3 projects: Crenshaw: 81.8% Regional Connector: 51% Purple Line Section 1: 37% Purple Line Section 2: 7% (Design 66% complete) It’s moving faster because it is skansa, not one of the criminal groups running the other projects. Skansa left a surplus of $200,000,000 from building expo, money that is being given to the tutor criminals for purple phase two, presumably because they’ve already defrauded that much money from tax payers. To be fair, Skanska is in charge of the Regional Connector project, which has a ~30% cost overrun and a 2-year delay. Skanska's bid for Purple Line Section 2 was $500 million more than Tutor-Perini.
|
|
|
Post by masonite on Jul 16, 2018 12:32:00 GMT -8
Here is the status of the Purple Line Extension Segment 1 (as of July 2018): • Overall Project Progress is 37% complete. • At the Wilshire/Western Retrieval Shaft, excavation and bracing continues with Level A strut installation and utility hanging in the south, and Level B waler installation in the north. • Concrete wall pours at Wilshire/La Brea Station needed to support TBM assembly are scheduled to complete at end of June 2018. Installation of rebar, embeds and HDPE continue along with mining support equipment in the south yard. • Excavation to Level D at the Wilshire/Fairfax Station continues, along with waler and strut installation. Excavation is now clear of the Paleo zone (Elevation 105’). Alimak installation to Level C and work on the pipe canopy tunnel eye is in progress. • Station excavation under the concrete deck at Wilshire/La Cienega Station continues. Work on the permanent power duct bank and hanging utilities moves forward. • Tunnel Boring Machines (TBMs) were delivered to Los Angeles in December 2017. TBM assembly at Wilshire/La Brea Station is scheduled for July 2018. Tunneling is planned to start in September 2018. Projected cost: $3,154M Projected opening: Nov 2023 metro.legistar.com/View.ashx?M=F&ID=6364702&GUID=15E9B6E8-1824-432E-8E0B-578E5BBA349BThis project seems to be moving at a much faster pace compared to the Crenshaw, Regional Connector, and Purple Line Section 2. In January, this was the completion percentage of the 4 projects: Crenshaw: 75% Regional Connector: 43% Purple Line Section 1: 25% Purple Line Section 2: 5% (Design 44% complete) metro.legistar.com/View.ashx?M=F&ID=5733197&GUID=CABC793F-86ED-47CB-901E-2DB239AC4813In July, this is the completion percentage of the 3 projects: Crenshaw: 81.8% Regional Connector: 51% Purple Line Section 1: 37% Purple Line Section 2: 7% (Design 66% complete) The Regional Connector continues to plod along at a rate of 16% completion per year. Meanwhile, Purple Line Section 1 is moving forward at 24% completion per year. If these rates were to hold, both projects would complete at nearly the same time (late 2021 vs early 2022). Obviously there are very different issues between the projects. In some ways the Regional Connector is a much more difficult project, due to the ancient utilities in Downtown L.A., the variety of station types, and the coming construction of new portals and bridge in Little Tokyo. The Purple Line, OTOH, is a straight shot, all underground, with major utilities only crossing its path at major arteries. It is increasingly looking like Crenshaw will be a 2020 opening given the mounting delays and budget problems. The Connector is most likely 2022 given the same reasons. The Purple Line seems to be the only going well right now, but that is only Section 1. Section 2 is too early to tell yet as it is in design work mostly.
|
|
|
Post by metrocenter on Jul 16, 2018 14:51:52 GMT -8
It is increasingly looking like Crenshaw will be a 2020 opening given the mounting delays and budget problems. The Connector is most likely 2022 given the same reasons. Off topic: I was shocked that Crenshaw Blvd is closed for through traffic for seven weeks at Leimert Park. The construction notice says it's for "street restoration". But why seven weeks? Anyway, Leimert Park looks like a warzone right now. I feel for the residents there.
|
|
|
Post by joshuanickel on Jul 16, 2018 15:35:35 GMT -8
It is increasingly looking like Crenshaw will be a 2020 opening given the mounting delays and budget problems. The Connector is most likely 2022 given the same reasons. Off topic: I was shocked that Crenshaw Blvd is closed for through traffic for seven weeks at Leimert Park. The construction notice says it's for "street restoration". But why seven weeks? Anyway, Leimert Park looks like a warzone right now. I feel for the residents there. There is alot to do. Here is a photo taken by Metro in late June: Crenshaw Boulevard restoration workThey have to remove the concrete deck and steel beams underneath, then they go and fill in and compact with dirt and gravel to rebuild the base for the road. Then you pour the new curbs, gutters, and sidewalk. Lastly the pave the road and reopen it. It takes a while but the road will look brand new when they are done.
|
|
|
Post by numble on Jul 16, 2018 19:18:39 GMT -8
|
|
|
Post by metrocenter on Jul 20, 2018 11:21:02 GMT -8
Streetsblog has an article about how the DOT is dragging its feet on releasing funds, including New Starts funds, to projects throughout America.
The projects in jeopardy are those which do not yet have FFGAs (Full Funding Grant Agreements). As the article explains:
Specifically, Section 3 of the Purple Line Extension does not yet have an FFGA. Section 3 is expecting/awaiting New Starts funds to the tune of over $1 billion.
Here's another article, from last year, about the White House's feet-dragging.
|
|
|
Post by numble on Jul 20, 2018 11:51:28 GMT -8
Streetsblog has an article about how the DOT is dragging its feet on releasing funds, including New Starts funds, to projects throughout America.
The projects in jeopardy are those which do not yet have FFGAs (Full Funding Grant Agreements). As the article explains:
Specifically, Section 3 of the Purple Line Extension does not yet have an FFGA. Section 3 is expecting/awaiting New Starts funds to the tune of over $1 billion.
Here's another article, from last year, about the White House's feet-dragging.
The DOT has also imposed additional conditions that have resulted in an increase to the estimated cost of the Purple Line by $190.9 million. I suppose these additional conditions applied to all New Starts applications will make some projects look more expensive or less cost effective. metro.legistar.com/LegislationDetail.aspx?ID=3532679&GUID=C59EAB58-BB7D-4D1A-96A4-96D973BB16B7&Options=ID%7CText%7CAttachments%7C&FullText=1
|
|
|
Post by culvercitylocke on Jul 20, 2018 12:13:48 GMT -8
In better news they’ve lowered the tbm shield into Wilshire la brea and are assembling the TBMs
|
|
|
Post by metrocenter on Jul 20, 2018 12:20:00 GMT -8
Reading the next paragraph, it looks like Metro is taking the safe and practical measure of not disputing the budget increase for now, since they don't want to rock the Federal funds boat:
|
|
|
Post by bluelineshawn on Jul 23, 2018 6:26:04 GMT -8
Reading the next paragraph, it looks like Metro is taking the safe and practical measure of not disputing the budget increase for now, since they don't want to rock the Federal funds boat:
Metro doesn’t have a letter of no prejudice yet? Uh oh. With Trump slow rolling FTA funding that could mean that receiving federal funds for segment 3 will happen later rather than sooner. If at all.
|
|
|
Post by culvercitylocke on Jul 25, 2018 9:16:34 GMT -8
The source has a story up and pics with the first TBm being assembled in the la brea pit.
|
|
|
Post by numble on Aug 29, 2018 19:47:59 GMT -8
|
|
|
Post by culvercitylocke on Aug 29, 2018 20:12:48 GMT -8
To be fair isn’t like forty percent of the regional connector the new tie in work? And they obviously haven’t started any of that.
|
|
|
Post by exporider on Aug 30, 2018 12:34:26 GMT -8
To be fair isn’t like forty percent of the regional connector the new tie in work? And they obviously haven’t started any of that. No, that doesn't sound fair to me. I'd guess ~10 percent for the new tie in work. Maybe 20% if you include the new station in Little Tokyo. But that depends whether you're talking about time or cost, and I'm pretty sure Metro is reporting costs, or more accurately value of the work completed.
|
|
|
Post by culvercitylocke on Aug 30, 2018 12:50:38 GMT -8
To be fair isn’t like forty percent of the regional connector the new tie in work? And they obviously haven’t started any of that. No, that doesn't sound fair to me. I'd guess ~10 percent for the new tie in work. Maybe 20% if you include the new station in Little Tokyo. But that depends whether you're talking about time or cost, and I'm pretty sure Metro is reporting costs, or more accurately value of the work completed. Don’t they have to demo existing track. Build a new bridge. Build a new trench. And then Build new rail tie ins? Bridge and trench and demo would comprise a lot of work for a 3 km line, at least thirty percent I would guess.
|
|
|
Post by metrocenter on Sept 4, 2018 13:53:46 GMT -8
They are very different projects. Both projects include a pair of bored tunnels, three cut-and-cover stations, and SEM crossovers.
The Purple Line Segment One is a longer project but is much simpler. It consists of a virtually straight tunneled route with a single tie-in. The only big complication is the expansion of the rail yard (in the Arts District).
The Regional Connector, on the other hand, includes three tie-ins (the wye connects to two separate branches), a new bridge, a 90-degree turn, a significant amount of cut-and-cover tunneling, and a much more complicated nest of utilities to relocate. Also, the three lines being tied together were built over the course of 25 years, and the Regional Connector needs to bridge the technologies of these three lines (for example, signaling and block detection).
|
|
|
Post by culvercitylocke on Sept 6, 2018 10:42:04 GMT -8
tBMs are undergoing final testing and will begin digging at the end of the month
AUR for rodeo station will be complete at the end of the month.
|
|
|
Post by culvercitylocke on Sept 6, 2018 21:24:07 GMT -8
Several months late but the ace gallery is finally scheduled for demo on sept 12. Once it’s gone, they can build the BH staging yard. Piles anticipated to start in 2019 for BH station and decking is anticipated to be 13 weekend closures for installation. Then 18 months to excavate the station box. Perhaps that means a tunneling drive for section 2 as soon as 2021.
|
|
|
Post by culvercitylocke on Sept 14, 2018 10:45:20 GMT -8
Purple line section three community meeting updates with an incoherent power point.
they have a schedule that says VA tunnel launch box construction starts in 2019 with tunneling beginning in 2020, but they're not even starting station excavation for UCLA or VA until 2021.
|
|
|
Post by numble on Sept 14, 2018 13:28:55 GMT -8
Purple line section three community meeting updates with an incoherent power point. they have a schedule that says VA tunnel launch box construction starts in 2019 with tunneling beginning in 2020, but they're not even starting station excavation for UCLA or VA until 2021. For Section 3, they are doing separate contracts for the tunnels and the stations. The tunnels contract has already been awarded, and its start is delayed due to the delay in getting a letter of no prejudice from the federal government. The stations contract has not yet been awarded. So it seems they expect to start on the tunnels before starting on the stations.
|
|
|
Post by numble on Sept 14, 2018 13:50:10 GMT -8
Purple line section three community meeting updates with an incoherent power point. they have a schedule that says VA tunnel launch box construction starts in 2019 with tunneling beginning in 2020, but they're not even starting station excavation for UCLA or VA until 2021. The construction plan was updated in March 2018 (I can’t seem to find the document), but it is mentioned in the June 2018 CEQA Addendum: media.metro.net/projects_studies/westside/images/final_ceqa_addendum_2018-0601.pdfThey are having overlapping schedules to accelerate the construction to be open by the Olympics.
|
|
|
Post by culvercitylocke on Sept 14, 2018 14:12:21 GMT -8
Purple line section three community meeting updates with an incoherent power point. they have a schedule that says VA tunnel launch box construction starts in 2019 with tunneling beginning in 2020, but they're not even starting station excavation for UCLA or VA until 2021. The construction plan was updated in March 2018 (I can’t seem to find the document), but it is mentioned in the June 2018 CEQA Addendum: media.metro.net/projects_studies/westside/images/final_ceqa_addendum_2018-0601.pdfThey are having overlapping schedules to accelerate the construction to be open by the Olympics. So just guessing here, but in order to do that they’d just tunnel nonstop to century city and the stations would excavate around the tunnels and remove those sections?
|
|
|
Post by numble on Sept 14, 2018 20:24:31 GMT -8
So just guessing here, but in order to do that they’d just tunnel nonstop to century city and the stations would excavate around the tunnels and remove those sections? It seems to be the case, with the tunnel contractor needing to provide excavation support walls at the ends of the station boxes. I guess if we can get a copy of the construction plan we could be more clear.
|
|
|
Post by numble on Sept 20, 2018 10:24:55 GMT -8
Segment 1 is 40% complete based on the report at Metro’s Construction Committee meeting as reported by Streetsblog LA’s Twitter account.
|
|
|
Post by culvercitylocke on Sept 20, 2018 11:22:00 GMT -8
The tbms have been ready to go since August, I wonder if there is some part of the machinery that did not pass inspection and they’re waiting on a replacement from Germany?
|
|